• March 11, 2014
  • News

Powertech has just completed pre-commissioning of the B8371 Mail Offplot and Utilities for the Gorgon LNG Barrow Island Project with the Offplot now successfully transported to site! The B8371 is the biggest Offplot building for the project in Brisbane, comprising a 33kV GHA Dual Incomer and Bustie with 20 feeders with 2 separate LV Comeca 400V boards, PMS and HVAC.

The commissioning was completed 2 weeks early with only minor hurdles. The B8330, also pre-commissioned by Powertech, was sent over shortly after. Currently the commissioned buildings count stands at 28 with 6 more to go.

Great effort by the Powertech team and thankyou and congratulations to all involved on a job well done!